Grid Interconnection Guide
Understanding the interconnection process for various utilities and project types in California
Select Utility
Interconnection Type
Process Information
PG&E Distribution Level Interconnection
Process Steps
- Submit Pre-Application Report Request (Optional)
- Submit Interconnection Request via PG&E's Interconnection Portal
- Technical Screening and Engineering Review
- Interconnection Agreement Execution
- Construction, Testing and Commissioning
- Permission to Operate (PTO)
Typical Timeline
3-12+ months depending on project size and queue position
Fees
Fast Track: $800-$1,000 for projects under 1MW, Detailed Study: $10,000-$50,000+
Interconnection Assistant
Ask questions about interconnection processes
Hello! I can answer your questions about interconnection processes. Ask me anything!