Grid Interconnection Guide

Understanding the interconnection process for various utilities and project types in California

Select Utility

Interconnection Type

Process Information

PG&E Distribution Level Interconnection

Process Steps

  1. Submit Pre-Application Report Request (Optional)
  2. Submit Interconnection Request via PG&E's Interconnection Portal
  3. Technical Screening and Engineering Review
  4. Interconnection Agreement Execution
  5. Construction, Testing and Commissioning
  6. Permission to Operate (PTO)

Typical Timeline

3-12+ months depending on project size and queue position

Fees

Fast Track: $800-$1,000 for projects under 1MW, Detailed Study: $10,000-$50,000+